Window Replacement in NSW Strata Apartments: Approval Timeline
For an eligible NSW minor renovation decided by a strata committee authorised through a by-law, the committee must give any refusal and its written reasons within 3 months of receiving the application. An approved by-law change must be registered within 6 months.
The details behind the answer
Classify NSW window work as common-property repair, eligible minor renovation requiring over 50% of votes cast in favour, or major alteration permitting at most 25% of vote value against under the standard approval routes.
Who controls the window and its maintenance?
Locate the window boundary on the strata plan and read any registered by-law assigning its repair or maintenance. Keep those documents with the opening mark. The NSW repairs and maintenance guidance explains the documents to check.
Define what has failed before choosing the replacement scope. A damaged operating component, a leaking frame interface and a proposed change to the external appearance create different decisions for the project team. Record the defect and the intended remedy against the apartment and opening mark.
List who signs the installation contract, who pays and who maintains the replacement. For a scheme-wide programme, name the owners corporation's contact; for an individual apartment, record the parties for that opening.
At this stage, the retrofit glazing and full replacement guide helps define how much of the existing assembly the project intends to retain. Use that scope consistently in the approval documents and supplier pricing.
Does the proposal need a minor or major renovation vote?
Eligible minor renovations need more than 50% of votes cast in favour, while the standard major-renovation route permits no more than 25% of the value of votes cast against. These are NSW procedures described in the government's strata renovation rules.
Double or triple glazing appears on the minor-renovation list, subject to exclusions for external appearance, structure and waterproofing. Work needing approval under another Act is also excluded from the minor route by §110(7)(e). Classify the actual window and interface scope before selecting its approval route.
Under §110(6A)–(6B), the 3-month process applies only to eligible minor renovations decided by a strata committee authorised through a by-law. A refusal requires written reasons within that period; the application is taken approved if the authorised committee does not refuse it within 3 months. Check receipt dates and compliance with those refusal and written-reasons conditions against the Act compilation in force 12 December 2025 and current NSW renovation guidance.
Present one settled proposal for the decision. Show the existing elevation, proposed frame appearance, opening arrangement and the affected wall or waterproofing interfaces. Where alternatives remain, give each one an identifiable drawing revision so the approved option can be carried into the contract.
Resolve responsibility for ongoing maintenance in the approval and any required common-property by-law. Changes to appearance or interfaces after approval should return to the responsible project adviser before the revised design goes to production.
Classify a NSW strata proposal before the vote
What is the approval-to-installation timeline?
Section 152 requires an owner proposing to alter the structure of that owner's own lot to give the owners corporation at least 14 days' written notice before starting. This is not a general 14-day notice rule for every common-property window project. An approved by-law change must separately be registered within 6 months; that filing deadline is explained in the NSW by-law process.
| Stage | Work to complete | Timing dependency | Result for the next stage |
|---|---|---|---|
| 1. Scope and responsibility | Map defects, boundaries and the intended change | Before submitting a defined proposal | Repair or renovation route identified |
| 2. Technical design | Resolve frame appearance, opening geometry and affected interfaces | Before the decision on that scope | Drawings showing frame appearance, opening geometry and installation interfaces |
| 3. Scheme decision | Obtain the applicable decision and record its conditions | Meeting or authorised committee process | Authorised scope and maintenance allocation |
| 4. By-law and other approvals | Complete a required by-law change and applicable building approvals | By-law registration within 6 months of approval | Effective documents and satisfied approval conditions |
| 5. Pre-start access and protection | Arrange access, protection, notices and installation sequence | At least 14 days' notice under §152 where an owner alters the structure of their own lot | A defined start date and occupied-building plan |
| 6. Delivery and handover | Install the accepted configuration, commission and close defects | After release conditions and site readiness | Opening records and maintenance handover |
From agreed scope to apartment handover
How are the building interfaces kept under control?
Draw the new frame against the existing wall, finishes and water-control layers, and name the contractor making good each junction. For a changed opening, use the replacement-opening measurement guide. If the frame is retained, record the replacement glass dimensions using the glass opening and cut-size guide.
Occupied apartments need an installation sequence that identifies temporary weather protection, access arrangements and when each opening will be secured. Agree the treatment of corridors, lifts and other shared access with the building's representative. Give residents the opening-specific work sequence so access arrangements remain practical.
When can the window package go into production?
Release production against 4 settled entries: the authorised opening schedule, accepted external appearance, approved installation interfaces and responsibility for the completed work. Tie them to a dated drawing revision. A quotation can be developed earlier, with unresolved selections kept visible.
Group a building-wide schedule by elevation and apartment access order, and label repeated units with their actual locations. For one apartment, put the proposed frame finish and sightlines beside the surrounding facade on the elevation.
At completion, connect each installed opening to its adjustment, demonstration and maintenance record through the window commissioning checklist. Close the remaining defects with a named responsible party and keep the finished configuration with the scheme's project records.
Price the authorised replacement scope
Send the opening schedule, proposed elevations and accepted wall-interface details to price the strata replacement package. Link each casement configuration to its authorised opening mark. Add the local performance requirements to the Australian project brief, and name the installer and the scheme's approval contact.
FAQ
Can I replace a strata window first and claim the cost later?
Do not assume reimbursement after ordering a replacement yourself. Responsibility for payment follows the ownership boundary, valid by-laws and the decision or applicable legal remedy for that work. Settle 3 responsibilities before ordering: who authorises the scope, who contracts and pays, and who maintains the completed work.
Does a strata committee's silence approve major window work?
No. The 3-month process applies only to eligible minor work submitted to a committee authorised by a by-law. Check whether the application was refused within the statutory period and whether the required written reasons were provided; major work still needs its applicable owners-corporation decision.
Is six months the normal approval time?
No. The 6-month period is the deadline to register an approved by-law change. The project's approval programme follows its design requirements, decision process and other applicable approvals.