Flat Roof Skylight Upstand Height: Size the Kerb Before Ordering

Compare UK 150 mm and US 4 in curb rules, then size a rooflight upstand, choose a prefabricated or timber kerb, and coordinate glass pitch and glazing.

Rooflight mounted on a raised curb above a grey flat roof membrane.
Answer in brief

Flat Roof Skylight Upstand Height: Size the Kerb Before Ordering

For a UK single-ply roof, SPRA guidance gives a minimum 150 mm upstand above the finished roof surface. The 2021 US IRC specifies a 4 in curb above the roof plane for unit skylights on roofs below 3:12, unless the product's installation instructions specify otherwise. Set the correct height datum and roof build-up before ordering the kerb.

1. How high should the upstand be above the finished roof?

The height is the exposed weathering protection above the adjacent roof finish. Insulation, ballast, paving and other finishes consume height when they rise around a kerb fixed to the structural deck.

The UK figure comes from SPRA Single Ply Design Guide 2020, section 3.17.1, printed pages 30–31 and Detail 1, Upstand – Minimum Height, including finished surface layers and the highest roof build-up around the junction. BSI now lists BS 6229:2025 as current, superseding 2018. SPRA upstand principles BSI current edition

New Zealand E2/AS1 fourth edition Figure 8.5.7.1A covers a membrane-roof penetration detail with an opening no larger than 1200 × 1200 mm. Use that figure within its timber-framed building scope of up to three storeys and 10 m. MBIE penetration detail

The US figure is specifically the 2021 IRC unit-skylight rule for roof pitches below three units vertical in twelve horizontal, a 25% slope, with its installation-instruction exception. Its datum is the roof plane. The applicable adopted code, roof assembly and product instructions govern the project detail. IRC R308.6.8

Where to measure exposed kerb height. Structural deck: The kerb is fixed at the deck; Roof build-up: Insulation, ballast or paving raise the adjacent level; Exposed kerb: Measure protection above the adjacent finished surface.
IMAGE NOTE

Where to measure exposed kerb height

2. Should I buy a prefabricated insulated kerb or build a timber upstand?

A prefabricated insulated kerb arrives with a defined section and matching seat for the rooflight. Published systems include flat tops for lanterns and pre-sloped tops for flat glass. Ordering it with the lid reduces the number of interfaces to set out on site, although the roofer still has to connect the waterproofing and the interior air seal.

A site-built timber upstand gives the builder more freedom around an existing opening or an unusual roof build-up. The timber supplies support; insulation, membrane coverage, corner treatment and the top seating surface are separate parts of the construction. An uninsulated timber box is not the same package as a factory insulated kerb.

Compare lid-only, lid-plus-insulated-kerb and complete flashing packages. Price the support, lifting access, roof waterproofing and interior air seal alongside the supplied components.

For heat loss, the joint between roof insulation and kerb matters alongside the glass specification. Our thermal performance guide explains why a glass U-value and the performance of the assembled opening are different figures.

3. What size should I order: the roof opening or the upstand?

A rooflight order involves 3 different dimensions: the structural opening, the finished upstand outside dimensions, and the clear daylight area. Some lantern systems use the outside faces of the supporting kerb as their order size; other rooflights use the structural opening. Substituting one for another can produce a lid that cannot seat on its support.

Assumptions: a rectangular opening 1000 × 1500 mm (39.4 × 59.1 in), with a 70 mm (2.76 in) kerb width on each side, and an order convention based on external kerb faces.

External kerb width = 1000 + 2 × 70 = 1140 mm (44.9 in). External kerb length = 1500 + 2 × 70 = 1640 mm (64.6 in). The 1000 × 1500 mm opening therefore leads to a 1140 × 1640 mm external-kerb order, before any product-specific fitting allowance.

Keep structural opening, external kerb and visible glass dimensions separately labelled on the same plan. Include whether the membrane and insulation fall inside the order dimension. The frame's weathering overhang and installation tolerance belong to the selected system; adding a generic allowance can make the finished kerb too large.

Example order based on outside kerb faces. Structural opening: 1,000 × 1,500 mm; Kerb thickness: 70 mm at each side; Outside dimensions: 1,140 × 1,640 mm before product-specific allowance; Order convention: Confirm the supplier uses the outside kerb faces.
IMAGE NOTE

Example order based on outside kerb faces

4. Does flat glass need a slope, and is a lantern different?

One UK rooflight maker publishes pre-sloped 5° insulated upstands for its flat-glass rooflights and level tops for its lanterns. The lantern glass rises towards its ridge, while the surrounding roof still needs its drainage fall.

Chinese GB 50345-2012 clause 4.10.4 recommends at least 5% drainage slope for a glass daylighting roof, formed by its supporting structure. Five percent is 50 mm rise per metre, approximately 2.9°; 5° is approximately 87 mm per metre. These values are not interchangeable. GB 50345

The same published upstand range includes nominal 150 and 300 mm kerbs, with 200 and 350 mm variants allowing 50 mm extra for firrings. Calculate exposed waterproofing above the completed roof separately from the supplied kerb height.

Assumptions: 180 mm (7.1 in) roof build-up above the structural deck and 150 mm exposed waterproofing. The termination needs to reach 180 + 150 = 330 mm (13.0 in) above the deck. A kerb terminating at 300 mm would leave only 120 mm (4.7 in). On a sloped kerb, calculate the clearance at every side.

5. Can a 75 mm threshold detail be used for a rooflight?

No. SPRA's 75 mm (3.0 in) concession concerns balcony or terrace door openings with a proprietary drainage channel and the other specified threshold measures. These include a fall away from the door, outlet and overflow provision or a lowered balcony kerb, and waterproofing extended beneath the door frame. The ordinary rooflight upstand remains 150 mm in that guidance. SPRA section 3.17.2(l)

6. Which glass belongs on the room side?

GB 50345-2012 clause 4.10.8 recommends laminated glass or laminated insulating glass for glass daylighting roofs. Clause 4.10.10(3) locates the laminated pane on the underside of the insulating unit, and 4.10.10(1) specifies a gas cavity at least 12 mm thick. GB 50345, pages 26–27

The 2021 IRC also distinguishes laminated inboard glazing from tempered or heat-strengthened panes when setting broken-glass retention-screen requirements. Laminated glazing meeting R308.6.2(1) is exempt from those screens under R308.6.5. IRC overhead glazing

Put the outer pane, cavity and inner laminate in order from outside to inside. Include coatings and the support arrangement in the glazing specification. Our laminated versus toughened glass guide explains the different breakage behaviour.

FAQ

Does a 150 mm timber kerb give 150 mm of waterproofing above the roof?

Only if its seating and waterproofing levels remain that high above the completed adjacent finish. A 300 mm termination above a deck with a 180 mm roof build-up leaves 120 mm exposed.

Should roof lantern dimensions match the hole in the roof?

Some lantern orders use the external kerb dimensions. With a 70 mm kerb on each side, a 1000 × 1500 mm opening produces an external kerb of 1140 × 1640 mm. Use the selected system's convention and fitting allowances.

Is a 5% glass-roof slope the same as 5 degrees?

No. A 5% slope rises 50 mm per metre, about 2.9°. A 5° slope rises approximately 87 mm per metre. Use the pitch stated for the selected glazing system.

HAVE A PROJECT SCHEDULE?

Let YULUX review your drawings before pricing.

Send us your window schedule, floor plans or photos. We review opening sizes, system direction, glass, hardware, finish and packing scope before quoting.

Continue planning your window and door project

Window, door and material selection

Get a Quote

Share your window schedule, architectural drawings, opening sizes or a project brief. We'll reply with system, glass, hardware, finish and export packing recommendations.

YULUX chat

AI assistant · Human support
⋯

AI guidance only; our team confirms pricing. ·

I am an AI, not a person. Share non-sensitive project needs only. Answers and search sources need verification; I cannot confirm pricing, agency status or contracts. The temporary session is kept in this browser tab and server memory, and clears after 30 minutes of inactivity. Privacy policy

Hi, I’m YULUX’s AI assistant. Ask about products, window and door systems, or partnership.