Pre-Shipment Inspection for Aluminum Windows
Inspect finished windows for identity, dimensions, glass, operation and packing before dispatch. For orders governed by GB/T 8478-2020, appearance and assembly receive 100% factory inspection, and Table 6 permits ±1.5 mm overall width or height deviation for dimensions up to 2000 mm. Mark a failed unit for correction and recheck it against the same drawing revision. GB/T 8478 source record
Where does the release decision tree begin?
Match the unit mark and drawing revision first. A mismatch puts the unit on hold. Correct identity leads to dimensions and handing, followed by operation, glazing, finish, accessories and packing.
Record each defect against 1 unit ID, then attach its corrective action, reinspection result and final release disposition. The window RFQ checklist supplies the approved order fields. Use the product’s handling and support arrangements while checking large units.
Which result sends a window back for correction?
| Observed symptom | First check | Release condition |
|---|---|---|
| Wrong opening direction or unit label | Drawing revision and opening ID | Correct configuration and traceable label |
| Sash rubs or lock needs force | Frame support, alignment and hardware | Normal operation after the recorded correction |
| Measured frame exceeds tolerance | Nominal size, measurement and adopted criterion | A passing remeasurement |
| Loose fittings or documents missing | Accessory schedule and delivery records | Complete items linked to the correct crate |
Every failed branch returns to a named correction and a recorded recheck.
What needs checking on every window?
GB/T 8478-2020 clause 7.2.1.1 requires 100% appearance/surface-quality and assembly-quality factory inspection. Apply the GB/T 8478 standard where it governs the order.
A scraping sash goes into the assembly row with its operation result and correction. A sliding-window assembly also needs its rollers, tracks and panel arrangement checked. Clauses 6.2–6.4 specify visual examination with a steel rule for appearance, dimensional gauges for size, and visual examination plus hand testing for assembly.
Check drainage openings against the approved section drawing; keep the specified water path clear of tape and debris. Inspect 6 groups before shipment: identity and quantity, dimensions and handing, glass and finish, hardware operation, packing and loose accessories, and shipment documents with defect closure.
| Check | Method and tool | Acceptance basis |
|---|---|---|
| Identity and quantity | Match marks, handing and count — Approved schedule, drawings | Approved revision and supply list |
| Frame and assembly dimensions | Measure the named dimension — Steel tape/rule, caliper, depth or feeler gauge as appropriate (6.3) | 5.3 / corresponding Table 6 row if adopted |
| Glass, finish and seals | Review visible configuration and surfaces — Steel rule, visual examination (6.2); camera | Approved glazing/finish; applicable 5.2 criteria and 6.2 viewing conditions |
| Assembly and hardware | Open, close, lock; examine joints; review specified drainage paths — Visual examination and hand testing (6.4) | 5.4 secure fittings, flexible controls, no binding; lock position/state to design; drainage to the approved section drawing |
| Packing and loose accessories | Compare protection, labels and contents — Packing plan, accessory list, camera | Order’s packing and accessory requirements |
| Documents and closure | Match unit/batch records and findings — Delivery documents, inspection register | Applicable 8.2 documents; 7.2.2 or 7.3.4 disposition |
Which frame dimensions pass the Chinese table?
GB/T 8478-2020 Table 6 allows ±1.5 mm overall width/height deviation up to 2000 mm, ±2.0 mm above 2000–3500 mm and ±2.5 mm above 3500 mm. A 2000 mm dimension is about 78.74 in and 3500 mm is about 137.80 in.
Assumptions for the width example are a 1200 mm specified finished-frame width under Table 6, an initial reading of 1201.8 mm and a corrected reading of 1200.7 mm.
With a 1200 mm specified width and ±1.5 mm tolerance, a 1201.8 mm reading exceeds the 1201.5 mm upper limit by 0.3 mm. The corrected reading lies inside the 1198.5–1201.5 mm interval. Enter both readings and their evidence IDs in the dimensional row.
Measure the finished construction dimension named on the drawing. Use the separate Table 6 rows for opposite-side and diagonal differences.
| Overall construction dimension | Permitted deviation | Approximate deviation in inches |
|---|---|---|
| Up to 2000 mm | ±1.5 mm | ±0.059 in |
| Above 2000 through 3500 mm | ±2.0 mm | ±0.079 in |
| Above 3500 mm | ±2.5 mm | ±0.098 in |
How many units enter a dimensional sample?
GB/T 8478-2020 clause 7.2.1.2 specifies 5% with at least 3 units for factory dimensional sampling, while Table 12 specifies 10% with at least 3 and marks dimensions for both factory and type inspection.
Clause 7.2.1.2 groups window and frame/sash assembly dimensional checks into 100-unit lots, with fewer than 100 also forming a lot. Within each lot, it requires separate random selection by type, variety, series and specification. Record these groups and their selected IDs so repeated standard units do not crowd out other configurations.
For the same dimensional item where both provisions apply, a buyer can specify a contractual sample large enough to satisfy both numerical minima, while retaining the required grouping and random selection. This larger-count approach is procurement advice. The original 5%/10% discrepancy still requires authoritative clarification before claiming that the text has been reconciled.
One unit keeps the original reading and the corrected result on the same card.
Which checks use a type-inspection sample?
Clause 7.3.2 selects a type-inspection lot from a factory-accepted batch of at least 100 units, with random specimen numbers taken from Table 12. Clause 7.3.3 calls for representative common elevations and sizes across the product’s uses, types, varieties and series.
GB/T 8478-2020 Table 12 assigns air, water and wind performance to applicable 3-specimen type tests, with routine factory checks recorded separately. Wind and water apply to external doors/windows; air also covers internal units with airtightness requirements.
How does AQL affect the agreed sampling plan?
A single-sample attributes plan uses 2 values, sample size n and acceptance count c, selected with the agreed quality level and sampling scheme. The NIST acceptance-sampling explanation describes random selection for lot disposition.
ISO 2859-1:2026 is the current third edition for AQL-indexed lot-by-lot inspection. An AQL-based agreement needs its edition, inspection level, lot and matching acceptance/rejection table. Keep its actual sample and decision rules identifiable alongside any adopted product-standard checks.
What happens after a sampled unit fails?
Under GB/T 8478-2020 clause 7.2.2, 1 failing unit permits a double-size retest, and more than 1 failing unit rejects the lot. An initially all-passing sample qualifies the lot. For the permitted retest, draw the doubled quantity from that lot; all retested items must pass for the factory-inspection lot to qualify.
Clause 7.3.4 applies 7.2.2 to type-inspection appearance, dimensional deviations, assembly and operating force. Failed performance items use double specimens from the batch for those failed items; all repeat results must meet the requirements.
A repair closes the individual finding after remeasurement or operation succeeds. Complete the applicable batch decision too, and connect its status to the payment milestone.
Which records travel with the shipment?
GB/T 8478-2020 section 8.2 names 3 document categories, a per-unit conformity certificate plus batch quality guarantees and installation/use instructions. The batch guarantee includes performance values/report number, quantities, sizes, finish and glass details.
Match the report’s configuration to the order. The Australian window test-report guide and Australia supply brief connect this record to destination requirements.
FAQ
How many inspection groups belong on a window shipment worksheet?
Check unit identity, dimensions, glass and finish, hardware operation, packing and accessories, then shipment documents. Hold wrong handing, binding sashes, out-of-tolerance frames and missing parts until the specific defect is corrected.
Does AQL 2.5 set a universal allowance for defective windows?
AQL 2.5 is a quality-level selection within an agreed sampling scheme. The matching plan determines sample size and acceptance or rejection counts, and its edition, lot and inspection level must be specified.
Can one failed dimension be repaired before dispatch?
Yes. Record repair and remeasurement. Clause 7.2.2 allows a double-size retest when exactly 1 sampled unit fails, with all retested items passing before the lot qualifies.
Which documents should follow each inspected window?
Under GB/T 8478-2020, each unit has a conformity certificate, while the delivery batch has a quality guarantee and installation/use instructions. Keep the 3 document categories linked to the correct unit or batch.